Hot Springs Board of Directors
September 9, 2025 Civic Briefing
Hot Springs Board Awards $298K Storm Water Drainage Contract, Approves $228K Wastewater Change Order
At its September 9, 2025 agenda meeting, the Hot Springs Board of Directors approved $410,937 in contract spending across two bid awards: a $183,140 change order expanding sidewalk work with Western Milight Commercial Construction, and a $227,797 change order for wastewater force main work with Diamond Construction — plus the underlying storm water drainage contract of $297,498 with JCON, Inc. was also awarded.
The short version
- The Board awarded a $297,498 storm water drainage repair contract to JCON, Inc. for three locations — Amber/Cedar Street, Delaware/Chelsea Street, and Lakeshore/Oxford Street — and approved a $150,100 budget adjustment to cover the work.
- The Board approved a $183,140 change order expanding sidewalk work with Western Milight Commercial Construction at the same unit prices from the original contract, bringing that total contract to $485,236.
- The Board approved a $227,797 change order for Diamond Construction to complete pipe and fitting connections at the Davidson Drive wastewater treatment plant headworks as part of the Gulfa Basin force main project.
- The Board acknowledged the city's July 2025 financial statements and updated bank account signatories to reflect a personnel change in the assistant finance director position.
- The Hot Springs Metro Partnership presented the August 2025 economic development report, highlighting workforce outreach at area schools, aerospace industry activity, and several local leaders receiving state recognition.
By the numbers
Money approved
| Item | Amount | Vendor | Vote | Source |
|---|---|---|---|---|
|
Storm Water Drainage Repairs — Amber/Cedar, Delaware/Chelsea, Lakeshore/Oxford
|
$297,498 | JCON, Inc. | Passed | item:4 |
|
Storm Water Drainage Repairs Budget Adjustment
budget transfer
|
$150,100 | — | Passed | item:4 |
|
Sidewalk Improvements Change Order
|
$183,140 | Western Milight Commercial Construction Company, Inc. | Passed | item:5 |
|
Gulfa Basin Force Main Change Order No. 1
|
$227,797 | Diamond Construction Company | Passed | item:6 |
| Total identified spending | $858,535 | |||
Major decisions
Economic Development Report — August 2025
- Item
- Presentation of the August 2025 Economic Development Report from the Hot Springs Metro Partnership, covering workforce outreach at area schools, aerospace industry activity, and state recognition of local leaders.
- Vote
- —
- Cost
- No cost specified
- Vendor / responsible
- Cole McCascal, Hot Springs Metro Partnership and Chamber
- Discussion level
- Brief Brief presentation
- Resident impact
- Informational presentation on economic development initiatives affecting the community.
- What the Board said or did
- Received and discussed the August 2025 Economic Development Report.
- Source
item:1
Storm Water Drainage Repairs — Three Locations
- Item
- Bid award — contract awarded to JCON, Inc. for storm water drainage repairs and improvements at three street intersections, plus a $150,100 budget adjustment to supplement the existing $140,440 storm water budget.
- Vote
- Passed
- Cost
- $297,498 contract; $150,100 budget adjustment requested to cover the gap between the contract amount and current budget
- Vendor / responsible
- JCON, Inc.
- Discussion level
- Brief Brief presentation
- Resident impact
- Drainage repairs at Amber Street and Cedar Street (damaged in April flooding), Delaware Street and Chelsea Street (currently causing home flooding), and Lakeshore Drive and Oxford Street. Residents near those intersections should expect construction activity.
- What the Board said or did
- Staff noted five competitive bids were received and JCON was the lowest responsible bidder. The April flooding damage and ongoing home flooding at the Delaware/Chelsea location were cited as reasons for the work. The Board passed the resolution.
- What remains unclear
- The record does not show the specific timeline for construction or the individual cost breakdown by project site.
- Source
item:4
Sidewalk Improvements Change Order
- Item
- Change order to an existing contract with Western Milight Commercial Construction Company, Inc. — adds $183,140 to expand the scope of 2025 sidewalk improvements using the same unit prices from the original bid.
- Vote
- Passed
- Cost
- $183,140 additional; brings the total contract to $485,236, which staff stated is within available funding for the year
- Vendor / responsible
- Western Milight Commercial Construction Company, Inc.
- Discussion level
- Brief Brief presentation
- Resident impact
- Additional sidewalk improvements will be completed at locations not specified in the available record. The work uses favorable pricing compared to prior years.
- What the Board said or did
- Staff explained that the original bid came in below estimate, leaving funding available, and that the city approached Western Milight about adding work at the original unit prices. The Board passed the change order.
- What remains unclear
- The record does not identify which streets or neighborhoods will receive the additional sidewalk work added by this change order.
- Source
item:5
Gulfa Basin Force Main Change Order No. 1
- Item
- Change order to the existing contract with Diamond Construction Company for Phase 2 of the Gulfa Basin force main project — adds $227,797 for pipe and fittings needed to connect the new force main to the Davidson Drive wastewater treatment plant headworks.
- Vote
- Passed
- Cost
- $227,797; funded from the wastewater bond fund. Staff noted this is less than 5% of the original contract but exceeds the $60,000 threshold requiring board approval
- Vendor / responsible
- Diamond Construction Company
- Discussion level
- Brief Brief presentation
- Resident impact
- This work connects the new sewer force main into the city's wastewater treatment facility at Davidson Drive. Completion of the connection is needed to bring Phase 2 of the project to full operation.
- What the Board said or did
- Staff explained that Diamond Construction paused the final connection work because of uncertainty about coordination with a separate contractor (identified in the transcript as 'Max Foot's construction') working at the same headworks location. The change order provides the materials to complete that connection. The Board passed the resolution.
- What remains unclear
- The record does not specify the identity or scope of the separate 'Max Foot's construction' project referenced, the overall timeline for completing Phase 2, or when the connection will be operational.
- Source
item:6
Approved without separate discussion
These items passed without individual debate as part of the consent agenda.
-
July 2025 Financial StatementsVote: Passed · No spending commitment — acknowledgment only
item:2 -
Bank Account Signatory ChangesVote: Passed · No cost
item:3
Locations affected
-
Amber Street and Cedar StreetStorm water drainage repairs; damage occurred during April 2025 floodingStatus: Scheduled
-
Delaware Street and Chelsea StreetStorm water drainage repairs; current conditions are causing home floodingStatus: Scheduled
-
Lakeshore Drive and Oxford StreetStorm water drainage repairsStatus: Scheduled
-
Davidson Drive Wastewater Treatment PlantChange order for pipe and fitting connection at plant headworks as part of Gulfa Basin force main Phase 2Status: Scheduled
-
Sidewalk improvement locations — multiple streetsAdditional sidewalk work under change order to Western Milight contract; specific streets not identified in the available recordStatus: Scheduled
Watch list
Open follow-up issues we'll check on in future briefings.
Sidewalk work locations not yet identified
OpenThe record does not identify which streets or neighborhoods will receive the additional sidewalk work added by the Western Milight change order.
- Why it matters
- Residents and the public need to know where construction activity will occur and which neighborhoods will benefit from the improved sidewalks.
- Next check
- The next briefing should check whether that list has been published by the Public Works department.
Max Foot's construction project scope unclear
OpenThe role and scope of the separate contractor referenced as 'Max Foot's construction' at the Davidson Drive wastewater headworks is not explained in the available record.
- Why it matters
- This separate project affects the timeline and coordination for completing the Gulfa Basin Phase 2 connection and bringing the wastewater improvements to full operation.
- Next check
- The next briefing should note whether that project affects the timeline for completing the Gulfa Basin Phase 2 connection.
Vote counts not recorded in transcript
OpenNo vote counts were recorded in the available record for any of the five votes taken at this meeting.
- Why it matters
- Vote breakdown indicates whether decisions were unanimous, close, or showed dissent, which is important for understanding board consensus and transparency.
- Next check
- The next briefing should check whether approved minutes provide the breakdown.
Source notes
This briefing is based on the public records below. Every claim above can be traced back to one or more of these sources.
- video: Meeting video
- agenda: Meeting agenda items 1-6
Transcript and 6 agenda items available; minutes not yet published and individual vote counts not recorded in source material.
- We do not invent facts.
- We cite source records.
- We distinguish what happened from what remains unclear.
- We use neutral language.
- We correct errors when found. See corrections.